In its pursuit to meet the growing power demand of the City Proper district, More Electric and Power Corporation (MORE Power) energized its newly acquired 33 Mega Volt-Amp (MVA) power transformer last March 26 and March 27.
This replaces the over 30-year-old transformer of the
previous distribution utility that conked out last January 2022.
MORE Power was able to acquire the slightly used transformer
from a major electric distribution utility in Luzon. The said transformer was
manufactured by Fortune Hitachi of Taiwan.
MORE Power tapped MIESCOR, a subsidiary of Meralco, for the
commissioning of the said new transformer.
The total cost of the equipment and commissioning was around
P50 million.
MORE Power President Roel Z. Castro is being interviewed by the media.
According to Roel Z. Castro, President and COO of MORE
Power, this new power asset is just part of the P1.9 billion investment of MORE
Power in its efforts to digitalize and modernize the distribution system.
Richard Ochava, president and chief operations officer of
MIESCOR, explained that the 30MVA transformer addresses the capacity problem of
the whole system. With the new transformer, the system’s capacity increased by
8%.
“It is future-ready, and maintenance-free. We have already
installed vacuum interruptors, so wala ng mga by-products in the operations of
tap changer. Ang mga bushings nya are made of polymer, so wala ng mababasag,”
Ochava said.
“Smart-ready na ang mga equipment natin. So, kung makikita
na natin ang operations remotely, lahat ng provisions namo-monitor natin
properly at handa na sya sa SCADA control system” he added
MORE MAJOR INVESTMENTS THIS YEAR
Castro related that in addition to the 10MVA Mobile
Substation which was installed in Megaworld last November 2020 and the new
33MVA substation, by September of this year, another 30MVA will be operational
in the said business district to cater to the increasing demand.
Overall, by end the of the year, Iloilo city would have a
total capacity of around 193MVA.
MORE Power allocated 1 Billion pesos for this year for the
development of said Megaworld Substation, purchase of 30 MVA Mobile Substation,
development of City Proper substation, improvement and upgrading of other
substations and sub transmission lines, construction of Control Center building
and associated equipment and reconductoring of various distribution lines.
Castro said that the modernization efforts of MORE Power are
aimed towards addressing systems loss factors, illegal connections and power
interruptions; reducing overloading; providing a cheaper and safer electricity
supply to consumers; and delivering efficient and reliable customer service.
NETWORK REHABILITATIONS IN THE PAST 2 YEARS
As to rehabilitation works, MORE Power has been massively replacing
old electric meters, undergoing replacements of dilapidated and wooden electric
poles, uprating distribution transformers, and installing conductors round the
clock.
Figure shows that they installed and replaced 1,715 poles,
559 distribution transformers, and 21,802 total electric meters.
There were also 619 electric meters on pole transferred and
330 elevated metering centers, installed 8.36 km neutral conductors, replaced
12.98 km of primary line, and 15.98 km secondary line.
Since the start of its operation, MORE Power was able to
install 240 Animal Guards, 189 Sets of Silicone Rubber Insulator, 31 Automatic
Circuit Reclosers (ARCs), and 15 Load Break Switches (LBS).
The installation of these equipment was able to avert large
percent of instantaneous causes or brownouts/ interruptions in the feeder.
Based on data, MORE Power’s System Average Interruption
Frequency Index (SAIFI) or the average number of interruptions a customer
experiences (as of Dec.31, 2021) and the System Average Interruption Duration
Index (SAIDI) showed 93-percent average decrease in interruption frequency and
85-percent average decrease in system interruption duration, respectively,
within one year.
EFFORTS TO LOWER RATES
In May 18 last year, the city’s sole power distributor
switched on its 69-kilovolt (kv) transmission station in Brgy. Banuyao, La Paz
district connecting 100 percent to the grid.
This has resulted to a major reduction in electricity rates
as MORE Power was able to gain access to cheap rates after contracting a
Geothermal power supply from Power Sector Assets and Liabilities Management
Corp (PSALM).
For the first year of its operation, MORE Power’s rate has
gone down to as low as P6.2071/kWh from the average of P13/kwh of the previous
utility.
With MORE Power, the electricity rate of Iloilo City is
lower compared to other private distribution utilities and electric
cooperatives in the country.
MORE Power through its Network Operations Department has
also launched a system loss reduction program dubbed as "Oplan
Valeria" and seized tons of electrical cables during a crackdown.
Oplan Valeria is a campaign against illegal electrical
connections or “jumpers.” The department has already conducted 1,549 operations
or inspections involving illegal connections.
Of the figure, 1,449 were sent with demand letters while 122
cases have so far been filed against power pilferers for violating Republic Act
7823 or the Anti-Pilferage of Electricity and Theft of Electric Transmission
Lines/Materials Act of 1994.
Meanwhile, the city’s sole power distributor was also able
to decrease system loss from 23.31 percent in May 2020 to 6.98 percent in
December 2021.
BETTER CUSTOMER SERVICE
MORE Power also earned the trust of Ilonggo consumers, from
ordinary power consumers to the business sector, because of its quick response
time.
The average response time, from the moment calls are
received until response team arrives on site, is 10 to 15 minutes.
From Feb. 19, 2020 to Dec. 31, 2021, MORE Power through its
various channels was able to respond and address a total of 486, 067 calls or
concerns.
Data shows that the social media platform with 48 percent is
the top choice of consumers in expressing their concerns.
MORE Power has responded to 233, 043 concerns thru social
media. This was followed by responses thru 24/7 hotline with 139,237 or 29
percent and thru its customer welfare desk with 113, 787 or 23 percent.
Moreover, since March 2020, a total of 22, 725 new
applicants have been energized or legally connected.
Also, through MORE Power’s Barangay Load Assessment Project,
hundreds of barangay facilities have been turned to legal connection.
Data showed that 567 barangay facilities were assessed, 52
barangays have started paying out of the 173 assessed barangays without meter,
45 barangays have ongoing application for new meter and 128 barangays with new
active meters.